Weekly Construction Updates

November 17, 2017

EV Graduate Residences Current Construction Updates
Current Construction Updates

Construction Impacts – Week Of November 20 and 27

Reconfiguration of parking at Studio 2 and Quillen continues. Parking changes to accommodate construction operations will continue through early December. There will be no reduction in the quantity of parking stalls.

For parking alternatives, visit https://transportation.stanford.edu/evgr.

Relocation of the trash enclosure at Studio 2 is underway. Anticipated completion: early December.

Concrete placement for building foundations are scheduled twice weekly through July 2018. For more information, view the November 9 Construction Advisory.

Crews will be on site Saturday, November 18, from 8am-5pm, working to mitigate water that has collected in the foundation trenches. Expect noise from pumps.

Hoskins, McFarland, and Thoburn Residents: underground utilities work will continue to impact pedestrian and bicycle circulation through early December.

Underground utilities work around the basketball courts will begin in late November. The basketball courts will remain open and available for use. Use caution when traveling in the area and follow posted detour signage.

Construction photos and drone footage are available online. Visit the gallery to watch the latest drone flight on October 20, 2017.

Safety first!

Use caution when traveling in the area and follow directional signage.

For your safety, please refrain from entering the construction site.